15 questions
Publisher
Testara

About this practice material

This page covers Testara's practice question bank for CIS-SPM, a certification listed under Servicenow. Questions use original, exam-style scenarios and are not questions from the official certification exam.

Testara is an independent practice platform and is not affiliated with, endorsed by, or authorized by Servicenow. The certification credential is issued by Servicenow, not Testara. Certification and provider names belong to their respective owners.

Start practicing

The guest demo does not save an attempt. Sign in before buying access.

Try 15 questions free

Available without signing in

Free sample questions

These 15 questions and their explanations are server-rendered so you can inspect the material before opening the interactive demo.

  1. Question 1 · 1

    Which property controls the changes in cost and resource plans with respect to the change in the start date of a demand or project?

    Choose one answer.

    • ‘Change Resource Plan, Cost Plan and Benefit Plan Start Date with Demand or Project Start Date Change’.
    • ‘Enable altering of planned date for task in WIP/Closed’.
    • ‘Rollup project start date from tasks’.
    • ‘Calculate ROI percentage based on a project's estimated cost and its net value’.
  2. Question 2 · 1

    Can an it_project_manager convert a task to a milestone?

    Choose one answer.

    • No, this can only be done by a system admin.
    • Yes, by right-clicking on the task in the Planning Console.
    • No, the PPS admin role is also required.
    • Yes, if the task is assigned to the project manager.
  3. Question 3 · 1

    What is the formula for Forecasted Utilization?

    Choose one answer.

    • Assigned Hours/Capacity
    • Confirmed Hours/Capacity
    • (Allocated Hours + Confirmed Hours)/Capacity
    • Allocated Hours/Capacity
  4. Question 4 · 1

    Use this table to configure the parameters displayed on a project card on the My Projects Space page of the Project Workspace.

    Choose one answer.

    • pm_toplevel_project
    • project_template_config
    • pm_home_page_config
    • pm_project
  5. Question 5 · 1

    If an it_project_manager does not want to equally distribute hours across the resource plan time frame, what allocation spread should be used?

    Choose one answer.

    • Front Load.
    • Back Load.
    • Any.
    • Even.
  6. Question 6 · 1

    If the ‘Move project for WIP projects’ property is enabled, project tasks associated with the project are also moved, except for tasks in which of the following states? (Choose two.)

    Choose all answers that apply.

    • Work in Progress
    • Closed
    • Pending
    • Open -
  7. Question 7 · 1

    Depending on the execution type selected for a particular project, one of these dashboards will also be available:

    Choose one answer.

    • User Manager Dashboard
    • Timecard Dashboard
    • PMO Dashboard
    • Project Summary - Waterfall Dashboard
  8. Question 8 · 1

    The Project management application supports two types of external dependencies. What are they? (Choose two.)

    Choose all answers that apply.

    • Change Dependency.
    • Hard Dependency.
    • Task Dependency.
    • Soft Dependency.
    • Milestone Dependency.
  9. Question 9 · 1

    The combination of the user and the assigned portfolio must be unique when adding a user to which registry?

    Choose one answer.

    • Stakeholder Registry.
    • Application Registry.
    • UX Page Registry.
    • Event Registry.
  10. Question 10 · 1

    Where do you define ‘Roles’ requested via resource plans?

    Choose one answer.

    • Roles under system security.
    • Resource roles under resource management.
    • Under skill management modules.
    • No need to define it differently, they are same as system roles.
  11. Question 11 · 1

    Which statement defines the Project Workspace?

    Choose one answer.

    • A central location to view of all projects in a portfolio to prioritize work
    • A central location for creating and managing projects
    • A central location for viewing and assessing business demands
    • A central location transform the navigation of lists and forms into an interactive graphical experience
  12. Question 12 · 1

    Where is planned cost calculated from when requesting resources from a group and when resource role is specified?

    Choose one answer.

    • The task rate cards.
    • The distribution costs.
    • The hourly rate of the specified role.
    • The CI rate cards.
  13. Question 13 · 1

    Which is the minimum role that has access to the Project Administration > Settings > Preferences-Project module?

    Choose one answer.

    • it_pps_admin
    • it_project_manager
    • it_program_manager
    • sys_admin
  14. Question 14 · 1

    What is a data copy of the current project's task, schedule, or structure that can be used for comparison reporting later?

    Choose one answer.

    • Commitment
    • Baseline
    • Accrual
    • Forecast
  15. Question 15 · 1

    If a lens has four entities, which entity within the lens structure would not have a parent reference?

    Choose one answer.

    • Second-level entity
    • Bottom entity
    • Top-level entity
    • Third-level entity

Each purchase applies to this certification. Prices are one-time payments, not monthly subscriptions.

Starter

$29 USD one time

Full access to one certification's question bank in standard practice mode for 60 days.

  • Full question bank for one certification
  • 60 days of access
  • Standard practice mode
  • Question notes and community discussions
  • Attempt scores and answer review

Professional

$49 USD one time

Full access to one certification's question bank, custom test controls and advanced analytics for 60 days.

  • Custom test builder
  • Timers and question selection
  • Randomized question and answer order
  • Advanced performance and weak-question analytics
  • Priority customer support
Try 15 questions free