About this practice material

This page covers Testara's practice question bank for MB-335, a certification listed under Microsoft. Questions use original, exam-style scenarios and are not questions from the official certification exam.

Testara is an independent practice platform and is not affiliated with, endorsed by, or authorized by Microsoft. The certification credential is issued by Microsoft, not Testara. Certification and provider names belong to their respective owners.

Start practicing

The guest demo does not save an attempt. Sign in before buying access.

Try 15 questions free

Available without signing in

Free sample questions

These 15 questions and their explanations are server-rendered so you can inspect the material before opening the interactive demo.

  1. Question 1 · 1

    A company produces rubber hose. Discrete orders accounts for raw material scrap. The scrap is reported through inventory movement journals. The company has noticed that most of the scrap that is recorded is due to start up that feeds the hose to the finishing process. In addition, the amount of scrap that is recorded is consistent regardless of the amount of hose being produced. You need to account for material lost during startup. What should you do?

    Choose one answer.

    • Enter the consumption amount on the line to match the actual amount used.
    • Do a case study for the scrap items and enter the average amount of scrap as separate line items on the Bill of materials.
    • Enter the amount of scrap that is consumed as constant scrap in the Bill of materials.
    • Enter the amount of scrap that is consumed as variable scrap in the Bill of materials.
  2. Question 2 · 1

    A manufacturer uses Dynamics 365 Supply Chain Management. The engineering department constantly revises product designs to stay current with the latest technology. The customer service department places orders for the products but frequently adds a prototype product version that is not yet operational. The manufacturer requires a solution that notifies customer service if a prototype version is selected on a sales order. You need to configure the solution. What should you configure?

    Choose one answer.

    • product release policy
    • product lifecycle states
    • version number rule
    • engineering product category
  3. Question 3 · 1

    You are the production supervisor at a chemical processing plant. You must track attributes for each batch of chemicals. Automated quality orders must be generated when a batch order for these chemicals is reported as finished. You need to ensure that the values of attributes are updated and tracked. What three actions should you perform? Each correct answer presents part of the solution. NOTE: Each correct selection is worth one point.

    Choose all answers that apply.

    • Create attribute types.
    • Create a test instrument for each attribute.
    • Set up batch attributes.
    • Assign the attributes to the appropriate test on the test group.
    • Assign the attributes to the chemicals.
  4. Question 4 · 1

    A manufacturing plant uses Lean manufacturing. Operators process Kanban consumption manually by using a mobile device. The production team must use automatic empty registration for some of the event Kanbans. Registration must occur when the last job of a Kanban is completed. You need to update the Kanban rule to meet this requirement. What Kanban setting should you update?

    Choose one answer.

    • Select to register as empty when handling units are received.
    • Select to manually register as empty.
    • Set a fixed Kanban quantity.
    • Select to register as empty when the source requirement is registered.
  5. Question 5 · 1

    A company produces generic and name-brand paper plates in the same factory using standard costing and using the same Bill of materials and routes to produce both products. The finance and production teams want a way to view individual raw material consumption costs in the ledger. You need to add a production group to the finished good to control postings to the ledger. What should you do?

    Choose one answer.

    • Update the cost of the generic finished good item.
    • Create a production group for the finished good item.
    • Create a production pool for the finished good item.
    • Create a new Bill of materials with alternate costs for the raw material.
  6. Question 6 · 1

    A company configures master planning to order large and expensive aluminum sheets that are only available at certain times of the year. The warehouse manager reports that replenishment levels are too high, causing inventory value to be over budget. In addition, the aluminum sheets take up too much space on the shop floor. You need to configure the appropriate replenishment method. Which coverage dimension should you use?

    Choose one answer.

    • Per period
    • Manual
    • Min/Max
    • Per requirement
  7. Question 7 · 1

    A manufacturing company is implementing production in Dynamics 365 Supply Chain Management. The production scheduler requires that machines not be scheduled to run concurrently when planning production. The scheduler also must be able to see the scheduling in a graphical view. You need to configure the system to meet the requirements. Which three options should you configure? Each answer presents a partial solution. NOTE: Each correct selection is worth one point.

    Choose all answers that apply.

    • bottleneck resource
    • finite capacity
    • operations scheduling
    • job scheduling
    • Capable to Promise
  8. Question 8 · 1

    A manufacturing company uses master planning in Dynamics 365 Supply Chain Management. The production planner increases the lead time of an item. On the next master planning output, the planner receives a cancel action message on existing purchase orders. The message includes a suggested earlier date for the planned purchase orders. The demand for the item has not changed since the original purchase order was placed. Dynamic negative days is not used. You need to resolve the issue. What should you do?

    Choose one answer.

    • Increase positive days.
    • Decrease positive days.
    • Decrease negative days to be less than the item lead time.
    • Increase negative days to be greater than the item lead time.
  9. Question 9 · 1

    A manufacturing company uses time and attendance in Dynamics 365 Supply Chain Management. The company requires that employees register time against each machine on the shop floor. You need to configure the system so that employees can register time. Which two configurations must be set up? Each answer represents a partial solution. NOTE: Each correct selection is worth one point.

    Choose all answers that apply.

    • time registration workers
    • registration workflow
    • machines as a resource
    • electronic timecard parameter
  10. Question 10 · 1

    You maintain responsible resource calendars and production orders for a manufacturing company. All production resources use the same production calendar. A machine in the facility is defective and must be closed for repairs for the next two days. You need to configure the resource calendar to close the resource for production for the next two days. What should you do?

    Choose one answer.

    • Navigate to the resource. Configure a calendar deviation to set the calendar to closed for the next two days.
    • Navigate to the calendar used for production and close the next two days.
    • Navigate to the resource. Change the calendar to closed on the resource.
    • Navigate to the resource group. Change the calendar to closed on the resource group.
  11. Question 11 · 1

    You are the lead product design manager at a Process manufacturing plant. A formula that produces egg yolks as a by-product. This by-product is added back into inventory at standard cost and can be used in other production batches. You need to select the by-product cost allocation. Which cost allocation type should you use?

    Choose one answer.

    • Per series
    • Percent
    • Recycled
    • Per quantity
  12. Question 12 · 1

    Case Study - This is a case study. Case studies are not timed separately. You can use as much exam time as you would like to complete each case. However, there may be additional case studies and sections on this exam. You must manage your time to ensure that you are able to complete all questions included on this exam in the time provided. To answer the questions included in a case study, you will need to reference information that is provided in the case study. Case studies might contain exhibits and other resources that provide more information about the scenario that is described in the case study. Each question is independent of the other questions in this case study. At the end of this case study, a review screen will appear. This screen allows you to review your answers and to make changes before you move to the next section of the exam. After you begin a new section, you cannot return to this section. To start the case study - To display the first question in this case study, click the Next button. Use the buttons in the left pane to explore the content of the case study before you answer the questions. Clicking these buttons displays information such as business requirements, existing environment, and problem statements. If the case study has an All Information tab, note that the information displayed is identical to the information displayed on the subsequent tabs. When you are ready to answer a question, click the Question button to return to the question. Background - A manufacturing company produces custom configured-to-order motorcycles. The company plans to implement Dynamics 365 Supply Chain Management. The company contains one legal entity located in Missouri where all production and warehousing operations occur. Customization options - The custom motorcycles have a variety of selections that can be selected in the listed order by the end customer, including the following: Current environment - Customization restrictions - The following restrictions on customizations are in place: Green color can only be sold with the Legend Trim. Orange color can be sold with the Sport or Legend Trim. The ML seat must be included in the Legend package. The MS seat must be included in the Sport package. Manufacturing facilities - The company includes the following manufacturing groups: Assembly and Plastic Molding. The Assembly group is responsible for assembling the motorcycles with purchased and manufactured goods. The Plastic Molding group is responsible for manufacture of all plastic parts used in the assembly area. Motorcycle manufacturing - The parts for the product assembly are picked from the warehouse and staged at the correct workstation by a warehouse operator for each production order. Plastic manufacturing - Plastic parts are molded using dyes that create multiple parts at once. The parts are machined in the same production process to remove excess plastic and add additional holes for assembly. Excess plastic is recycled back into the feedstock of the same color plastic chips for use in the molding process. Metal parts - Raw metal parts are purchased fully machined but without primer or paint. The parts are subcontracted to a vendor for primer and paint based upon the color requirements. Facility - The company has a single warehouse that supports both the assembly and plastic manufacturing areas. The warehouse consists of three aisles with 15 bins and three shelves. The facility has no Wi-Fi capacity but has hardwired terminal stations throughout the assembly production line Transactions are currently completed by office staff. Raw materials transfer must support capacity constraints for paint and primer. Requirements - Sales orders - The company has the following requirements for sales order: During the configuration of a sales order, invalid combinations must be prevented. Each configuration must create a unique bill of material (BOM) and Route based on options selected. Sales pricing for the sales order must be based upon options selected. Due to emissions regulations, the motorcycles cannot be sold to the state of California. Motorcycle manufacturing - The company has the following requirements for motorcycle manufacturing: Schedule labor only at the labor pool level without machines by day. Produce motorcycles within a scheduled day in any order. Record actual production labor with start/stop times. Record manager approval of labor entered prior to posting. Post actual material consumption after production is finished. Plastic manufacturing - The company has the following requirements for motorcycle manufacturing Schedule both labor and machines. Adjust schedules by using a Gantt chart. Backflush standard labor by operation. Post actual material consumption at the start of production. Track and allocate costs to the excess plastic. Report multiple molded part numbers during the same production run. Determine the correct mold to use on a production order. Generate a batch number for each production order. Metal parts - The company has the following requirements for metal parts manufacturing: Schedule shipments to the vendor for painting. Receive painted parts into inventory from the vendor. Track vendor inventory levels. Defaults - You must configure defaults for manufacturing execution production orders to meet the following requirements: Ensure accuracy for production order pick list posting. Ensure correct pick list creation. Issues - In the current system, the company cannot calculate overhead rates and determine the breakdown of material, labor, machine, and overhead costs for production. The company is manually calculating an 8% overhead on materials and posting a journal manually. You need to set up the state control for sales of motorcycles. Which two actions should you perform? Each correct answer presents part of the solution. NOTE: Each correct selection is worth one point.

    Choose all answers that apply.

    Question illustration 1
    • Create an exclusive restricted product list for Missouri and add the motorcycle part to the list.
    • Create an exclusive restricted product list for California and add the motorcycle part to the list.
    • Create an inclusive restricted product list for United States and add the motorcycle part to the list.
    • Create an inclusive restricted product list for United States. Do not add the motorcycle part to the list.
  13. Question 13 · 1

    A manufacturing company uses time and attendance in Dynamics 365 Supply Chain Management. Break times are paid. The cost of a break time must be charged at the pay rate of the job in progress when the break starts. You need to configure the break times to charge against the job in progress. Which two actions should you perform? Each answer presents a partial solution. NOTE: Each correct selection is worth one point.

    Choose all answers that apply.

    • Set Production Order Cost Category to Yes.
    • Set Direct Payroll Cost Standard Time to Yes.
    • Set Direct Payroll Cost Standard Time to Allocate.
    • Set Production Order Cost Category to No.
    • Set Direct Payroll Cost Standard Time to No.
  14. Question 14 · 1

    Note: This question is part of a series of questions that present the same scenario. Each question in the series contains a unique solution that might meet the stated goals. Some question sets might have more than one correct solution, while others might not have a correct solution. After you answer a question in this section, you will NOT be able to return to it. As a result, these questions will not appear in the review screen. A company implements Dynamics 365 Supply Chain Management and configures the system to support process manufacturing. The company manufactures pain-relieving lotions. Several of the primary ingredients are delivered at different concentrations depending on the ingredient and vendor. IngredientA is the primary active ingredient in the lotion. IngredientB is used as a compensating ingredient. You need to ensure that the system is set up to support the manufacturing process. Solution: Create a formula version for each concentration level. Does the solution meet the goal?

    Choose one answer.

    • Yes
    • No
  15. Question 15 · 1

    Note: This question is part of a series of questions that present the same scenario. Each question in the series contains a unique solution that might meet the stated goals. Some question sets might have more than one correct solution, while others might not have a correct solution. After you answer a question in this section, you will NOT be able to return to it. As a result, these questions will not appear in the review screen. A company implements Dynamics 365 Supply Chain Management and configures the system to support process manufacturing. The company manufactures pain-relieving lotions. Several of the primary ingredients are delivered at different concentrations depending on the ingredient and vendor. IngredientA is the primary active ingredient in the lotion. IngredientB is used as a compensating ingredient. You need to ensure that the system is set up to support the manufacturing process. Solution: Set up the IngredientB formula line as a phantom BOM. Does the solution meet the goal?

    Choose one answer.

    • Yes
    • No

Each purchase applies to this certification. Prices are one-time payments, not monthly subscriptions.

Starter

$29 USD one time

Full access to one certification's question bank in standard practice mode for 60 days.

  • Full question bank for one certification
  • 60 days of access
  • Standard practice mode
  • Question notes and community discussions
  • Attempt scores and answer review

Professional

$49 USD one time

Full access to one certification's question bank, custom test controls and advanced analytics for 60 days.